RICHMOND – Praising the developer for submitting a thorough, detailed application, members of the Planning Board unanimously approved the master plan for a significant expansion of Riverhead Building Supply at 38 Kingstown Road.
The expansion is welcome news for the town, which, for decades, has tried to lure businesses, since upon completion, the facility will be one of Richmond’s largest commercial taxpayers.
Because the application, submitted by Riverhead owner GX3 LLC of New York State, is categorized as a major land development, it requires four stages of review. The proposal was first submitted to the Planning Board in January and board members visited the site in February. The master plan approval is the second step in the approval process.
Town Planner Shaun Lacey described the proposal, which will involve the construction of a 200,000-square foot warehouse and distribution facility.
“The subject property is a split-zone parcel which is zoned as general business and industrial,” he explained. “The proposed scope of work is within the general business zone, where warehouses are permitted.”
A traffic study, prepared by the developer and peer-reviewed by a consultant for the town, indicated only minor increases in traffic volume.
Lighting on the proposed structures would be dark sky - compliant and the parcel would be landscaped to provide screening along the perimeter.
Darren Hayward of CLA Engineers Inc., presented the plans for the project and answered questions from board members.
“The lot’s about 48 acres in size,” he said. “We have Stop & Shop to the West and Richmond Sand and Stone to the North and East of the site. The site currently operates Riverhead’s commercial storage and retail sales facility…There’s already several existing buildings, totaling about 40,000 square feet, and approximately 11 of the 48 acres are currently in use. The development proposes expanding the existing operations with a phased, 200,000 - square foot building with a combination of ambient and air - conditioned space. We’ve included office space, loading docks in both Phases I and II - [with] associated parking. The additional development will add 15 acres of new development, bringing the full build-out of that area to approximately 26 acres.”
Lacey described the proposal as consistent with the town’s comprehensive plan and recommended the board approve the master plan.
“This is a development that meets several of the provisions of the town’s comprehensive plan,” he said. “It happens to comply with all the zoning ordinance provisions, so, for that reason, I’ll recommend the board approve the application tonight, subject to the findings and conditions.”
A $20 million investment
With the subject of economic development dominating town meeting agendas in recent months, the Riverhead expansion represents a $20 million investment in the town. It’s especially good news for Town Council President Mark Trimmer, who has been accused by political opponents of not doing enough to attract commercial developers to Richmond.
Reached Wednesday, Trimmer said he had known about the pending Riverhead investment but had not disclosed the news until after the Planning Board meeting. He also hinted at additional commercial investments to come.
“The fact that they’re going to invest that kind of money in the town is amazing,” he said. “We need that kind of investment. That’s one, and there’s quite a bit more going on.”
Next steps
Board members had a few comments and questions.
Board Chairman Philip Damicis noted that the storm water drainage documented in the plan would require frequent cleaning to be efficient.
“It is a long way, and hopefully, you’ve got a lot of clean-outs and whatever you need to keep that from getting clogged up,” he said.
Hayward replied that modifications had already been made to the drainage configuration.
“We made this submission a couple of months ago now, and to your point, we are well on our way on the preliminary design now and we’re getting into more detailed design, and our drainage design in that area has actually changed, so all the drainage from those depressed loading docks are actually going West into that basin now.”
“That makes more sense,” Damicis said.
Board member Melissa Chalek noted that the landscaping plan included butterfly bush and asked if that shrub, which is considered invasive, could be replaced with something more sustainable.
The developer will now continue with the state and federal permitting processes. The next step will be the submission of the preliminary plan which will involve a more detailed review and a public hearing.